PERT calculator: expected duration and probability of meeting the deadline
Work out the PERT expected duration from the optimistic, most likely and pessimistic estimates, its standard deviation and the chance of finishing on time, or the deadline for a probability.
Asking "how long will it take?" usually gets an over-optimistic figure. PERT asks for three: how long it would take if all goes well (optimistic, a), the most usual (most likely, m) and how long if almost everything goes wrong (pessimistic, b). From them you get a more realistic expected duration and, above all, how much uncertainty there is. It is used to plan building work, maintenance shutdowns, installations and engineering projects.
Expected duration and deviation
Example: building an electrical panel. If all goes well, 4 days; normally, 6; if materials are missing and there are changes, 14. tₑ = (4 + 4 · 6 + 14) / 6 = 7 days and σ = (14 − 4) / 6 = 1.67 days. The expected duration is above the most likely one because possible delays are bigger than possible gains.
These formulas come from assuming a beta distribution between a and b with its mode at m. The triangular mean, (a + m + b) / 3 = 8 days, gives more weight to the extremes.
Probability of meeting a deadline
With a 9-day deadline: z = (9 − 7) / 1.67 = 1.2 and the probability of finishing on time is Φ(1.2) = 88.5 %. The other way round, to commit with 95 % confidence you have to quote tₑ + 1.645 σ = 9.74 days. This part uses the normal distribution, as classic PERT does, and is more reliable for a project with several tasks than for a single one.
| Confidence | Deadline |
|---|---|
| 50 % | tₑ |
| 84 % | tₑ + σ |
| 95 % | tₑ + 1.645 σ |
| 99 % | tₑ + 2.326 σ |
A project with several tasks
Work out tₑ and σ² for each task on the critical path (the longest sequence, the one that sets the end). The project duration is the sum of the tₑ and its variance the sum of the σ²: the project deviation is the square root of that sum, not the sum of the deviations. Three tasks with σ = 1.67 days give σ = √(3 · 2.78) = 2.89 days, not 5.
How to use the calculator
Type the three estimates and the deadline to see the probability of meeting it, or the probability you want to see which deadline to give. You can also leave one of the three estimates empty if you know the deadline and its probability. Durations accept hours, days, weeks or months.
Frequently asked questions
How is the PERT expected time calculated?
tₑ = (a + 4m + b) / 6: the optimistic, four times the most likely and the pessimistic, divided by six. With 4, 6 and 14 days: (4 + 24 + 14) / 6 = 7 days. The standard deviation is (b − a) / 6 = 1.67 days.
What is the chance of finishing in 9 days?
z = (9 − 7) / 1.67 = 1.2; Φ(1.2) = 88.5 %. For 95 % confidence you need to quote tₑ + 1.645 σ = 9.74 days.
How do I work out a project with several tasks?
Add up the expected durations of the critical-path tasks and add up their variances (not the deviations); the project deviation is the square root of the sum. Type those totals as a single task, with a = tₑ − 3σ, b = tₑ + 3σ and m = tₑ.
Why PERT and not the average of the three?
Because task durations usually have a tail to the right (it is easier to run late than early) and PERT assumes a beta distribution that gives more weight to the most likely value. The triangular mean (a + m + b) / 3 gives more weight to the extremes and comes out somewhat more pessimistic.